June 2017

Construction Junctions are Infrastructure Planning and Facilities’s monthly public presentations designed to update/inform the public of various projects currently in design, nearing construction and under construction

Summer road, parking lot and ramp projects

  • Please see the PDF of the presentation to view maps of affected areas

Olin Health Center - renovations for student health and wellness - phase one

Project background

  • During 2016, an action committee (comprised of leadership and staff from Student Health Services, Psychiatry Services, Counseling Center and members of faculty) was charged with developing a strategy to integrate the university's counseling and psychiatric services for students.
  • The committee recommended establishment of a new multi-disciplinary, inter-professional model of care and services for students, that not only integrates the MSU Counseling Center and Olin Psychiatry Clinic into the new Counseling and Psychiatry Services unit (CAPS), but that will also co-locate that new unit with the Sexual Assault Program and Student Health Services, including primary care and health promotion.
  • The physical co-location is necessary to provide an appropriate continuum of care for students.

Project goals

  • Provide a shared and expanded space for the newly formed Counseling and Psychiatry Services unit (CAPS).
  • Co-location necessary to support the provision of an appropriate continuum of care for students.
  • CAPS unit to be in place on the third floor of Olin for the start of fall semester 2017.

Project scope

  • Renovation primarily to the third floor of Olin Health Center to include:
    • Selected demolition, including asbestos abatement
    • Creation of reception/waiting area including check-in/check-out
    • New and renovated office/therapy space
    • New and renovated public restrooms
  • HVAC installation and modification
  • Very limited modifications at Linton Hall, Olds Hall and Student Services necessary to accomplish the CAPS location on the third floor of Olin

Timeline

  • Construction start: May
  • Construction complete: August

Parking Lot 92 – reconstruction and expansion

Project milestones (a list of accomplishments/project phases completed during the past month)

  • Site clearing of the lot expansion area is complete
  • Demolition of the existing renovation areas is complete
  • Majority of new storm sewer system is installed
  • Undercut of existing unsuitable subsoils and replacement with new gravel subbase has begun

Impact updates (a list of any pedestrian, traffic, building occupant, facility impacts expected in the coming month)

  • Lot 92 is completely closed throughout the summer.
  • MSU Police advise alternative parking in Lots 97 and 91
  • The Service Road pedestrian pathway remains open along the north side of the road with construction safety barriers

Solar carports (electrical distribution – renewable energy)

Project milestones (a list of accomplishments/project phases completed during the past month)

  • Foundation ground anchors (micropiles) installed in five of eight phases in Lot 89 and four of seven phases in Lot 91
  • First carport canopy, less solar panels, installed in Lot 89

Impact updates (a list of any pedestrian, traffic, building occupant, facility impacts expected in the coming month)

  • Open parking areas in Lot 89 will alternate as micropiling phases continue
  • Canopy erection to begin in Lots 89 and 91. The west phase in Lot 89 and the east phase in Lot 91 will remain closed during installation

IM Sports West – replace pool and locker room HVAC systems

Project milestones (a list of accomplishments/project phases completed during the past month)

  • The indoor pool was drained and filled with scaffold walls and wood decking that will support mechanical lifts
  • Completed the demolition of the two mechanical rooms, locker rooms and the pool ceiling.

Impact updates (a list of any pedestrian, traffic, building occupant, facility impacts expected in the coming month)

  • Occupants and users of the IM are restricted from the southeast corner of the first floor corridors, indoor pool and locker rooms associated with the pool.
  • Coach’s offices will be vacated for ceiling abatement and removal for new air conditioning installation

Interdisciplinary Science and Technology – construct original building

Project milestones (a list of accomplishments/project phases completed during the past month)

  • Project began with the demolition of parking lot 96 which is complete
  • Site plans for the expansion of parking lot 100 complete
  • Re-routing of the Bott Nursing building geo-thermal lines complete

Impact updates (a list of any pedestrian, traffic, building occupant, facility impacts expected in the coming month)

  • Both pedestrians and traffic have been greatly impacted with the closure of Parking Lot 96 and the drop off point directly in front of Clinical Center A.
  • Patients to Radiology and Neurology are now parking in Lot 100. A shuttle service has been added in the lot to help patients to and from the buildings.
  • The drop off directly in front of the Clinic has been closed and traffic is directed into Parking Lot 90 for drop off.
  • The sidewalk along the south side of Service Road is closed, with pedestrians being routed to the sidewalk to the north.
  • The expansion to Parking Lot 100 is expected to be complete in mid June. This will move parking closer to the entrances of Radiology and Neurology again and create a new drop off area directly in front of the Clinic.

Engineering Research Complex – addition and renovations

Project milestones (a list of accomplishments/project phases completed during the past month)

  • The design phase is complete
  • Pre-engineered building walk through on May 17

Impact updates (a list of any pedestrian, traffic, building occupant, facility impacts expected in the coming month)

  • No additional impacts expected

Veterinary Medical Center – alterations to room E100 and corridor

Project milestones (a list of accomplishments/project phases completed during the past month)

  • Demolition of the existing auditorium seating is complete
  • The ceiling has been removed
  • Underground utilities have been completed
  • Plastering of the walls has started

Impact updates (a list of any pedestrian, traffic, building occupant, facility impacts expected in the coming month)

  • The west corridor continues to be closed to through pedestrian traffic
  • Increased construction traffic will continue at the northwest drive

Bessey Hall – alterations to first and second floors

Project milestones (a list of accomplishments/project phases completed during the past month)

  • Demolition and abatement complete on second floor
  • New masonry alcove walls are in construction
  • Project is on schedule with estimated completion on Aug. 17

Impact updates (a list of any pedestrian, traffic, building occupant, facility impacts expected in the coming month)

  • Access remains open to the elevator and to the office suites during construction.

Engineering Research – Hulett Rd. – Addition No. 2 – Food Processing Innovation Center

Project milestones (a list of accomplishments/project phases completed during the past month)

  • Contractor has mobilized and construction has started
  • Demolition is 90% complete

Ralph Young Track – replace field hockey playing surface

Project milestones (a list of accomplishments/project phases completed during the past month)

  • Removal of existing artificial turf and e-layer
  • Subbase graded to new elevation
  • Irrigation upgrades are ongoing
  • Porous asphalt layer was installed the week of May 29

Impact updates (a list of any pedestrian, traffic, building occupant, facility impacts expected in the coming month)

  • Sidewalk north of track continues to be closed throughout duration of the project

Hubbard Hall exterior masonry repair and window replacement

Project milestones (a list of accomplishments/project phases completed during the past month)

  • Construction has begun with the removal of window caulking.
  • The first shipment of new windows has been received.

Impact updates (a list of any pedestrian, traffic, building occupant, facility impacts expected in the coming month)

  • South Hubbard Hall is closed for the summer.

Facility for Rare Isotope Beams

1855 Place

Project milestones (a list of accomplishments/project phases completed during the past month)

  • Single student apartment buildings B2 and C2 have reached substantial completion (excluding exteriors)
  • Exterior site work and landscaping efforts have significantly increased this month
  • Single student apartment buildings B1 and C1 punch lists have been generated.

Impact updates (a list of any pedestrian, traffic, building occupant, facility impacts expected in the coming month)

  • Parking Ramp 7 elevator will be experiencing a brief temporary shut down sometime in the month of June for a warranty repair

Breslin Student Events Center – facility upgrades

Project milestones (a list of accomplishments/project phases completed during the past month)

  • Demo of Quad 2 and 3 is complete
  • Elevator demo complete
  • Magic Johnson statue relocated to permanent location
  • Glass curtain wall at Hall of History complete

Impact updates (a list of any pedestrian, traffic, building occupant, facility impacts expected in the coming month)

  • Parking Lot 63 closures commencing on May 30
  • Site work at the south side of Breslin to commence June 5
  • Pedestrian detours to south side of Shaw Lane and west side of Harrison Road required during Lot 63 work

Spartan Stadium – South End Zone Addition

Project milestones (a list of accomplishments/project phases completed during the past month)

  • Plaza concrete work is complete
  • Hollow core roof decking has been installed
  • Precast brick veneer and roofing installation has started

Impact updates (a list of any pedestrian, traffic, building occupant, facility impacts expected in the coming month)

  • Lot 79 will be shut down from June 19 through Aug. 21.
  • Pedestrian detour will be in place on south side of Shaw Lane and Chestnut Road

Spartan Stadium – install permanent field lighting

Project milestones (a list of accomplishments/project phases completed during the past month)

  • Caissons and structural steel installed for lighting
  • Electrical panel upgrades complete
  • Electrical installations are ongoing

Impact updates (a list of any pedestrian, traffic, building occupant, facility impacts expected in the coming month)

  • Partial shutdown of Stadium Drive on the east side of the Stadium is required for light pole installation. No through traffic during shutdowns.
  • Pedestrian detours are required at west side of Stadium for light installation on west tower.

Grand Rapids – real estate and research facility development

Project milestones (a list of accomplishments/project phases completed during the past month)

  • Punchlists in progress for floors one through four
  • Furniture installation is in progress
  • Site work is in progress and will be completed on July 15

Impact updates (a list of any pedestrian, traffic, building occupant, facility impacts expected in the coming month)

  • Michigan Street reconstruction in progress through July
  • Westbound I-196 reconstruction and bridge widening occurring through January 2019
  • Building dedication will be held on Sept. 20
  • Researcher move-in will occur in November/December

Construction Junction presentations will be available online around the seventh of each month

Meeting presentation

June 2017 (pdf)