Trowbridge Road repaving - Harrison Road to Oyer Speech and Hearing

Project phase: Construction

Project background

  • MDOT constructed the campus extension of Trowbridge Road in 2001.
  • Trowbridge Road has evolved into the primary entrance to campus. As such, pavement deterioration has necessitated replacement. 

Project detail

  • Goal is to achieve a 20-year life span for the new pavement.

Project scope

  • Mill and resurface both eastbound and westbound roadways (four lanes and two bike lanes) from Harrison Road to Oyer Speech and Hearing parking lot.

Impacts

  • Pedestrian and vehicular circulation will be affected
  • Phase 1: Eastbound Trowbridge Road (all traffic lanes) from Harrison Road to Red Cedar Road will be closed June 5-16
  • Phase 2: Westbound Trowbridge Road (all traffic lanes) from Red Cedar Road (by Communication Arts and Sciences building) to Harrison Road will be closed June 17-30
  • Final phase: East- and Westbound Trowbridge (all traffic lanes) from Trowbridge/Red Cedar Road intersection to Wilson Road will be closed June 23-30

Timeline

  • Construction start: June 5, 2017
  • Construction completion: July 28, 2017

Budget

  • $940,000,which includes a $35,250 contingency.  The project will be funded by the general fund - capital renewal.

Questions, comments, concerns?

CP16204

DETOUR MAP

Interactive detour map with current closure information for motorists and pedestrians.