Asbestos abatement

What is being done?

Abatement of asbestos-containing materials in rooms 340 and 342. During this project approximately 1200 square feet of ACM floor tile and mastic will be removed as well as demolition of walls and ceiling.

Why is this being done?

To accommodate renovations in the building.

How will this impact building occupants?

The requester of this project is responsible for the removal of any furniture or other items which may inhibit the ability of the contractor to perform this abatement. Asbestos work areas are strictly off limits to persons who are not trained or directly involved with the project. Please respect all warning signs and danger tape.

Who can I contact for more information?

Matt Smith, Planner/Inspector/Analyst, at (517) 898-5382 or smit2620@msu.edu  or IPF at (517) 353-1760.