Hubbard Hall 2019 exterior masonry restoration and window replacement

Hubbard Hall

Project Information

Phase

  • Construction

Background

  • Hubbard Hall opened in 1966 and is the tallest residence hall on campus, standing at 12 floors in two separate towers - north and south.
  • A 2013 study of its structural condition revealed a number of issues which must be addressed to keep the building safe and functional.
  • The work will be completed in four phases:
    • Southeast façade – 2016 (complete)
    • Southwest façade – 2017 (complete)
    • Northeast façade – 2018 (complete)
    • Northwest façade - 2019

Scope

  • The project will include masonry repairs to the facade and removal and replacement of windows

Impacts

  • Summer programs using residence halls–project limits use of Hubbard Hall to one living wing each summer 2016-2019.

Schedule

  • Phase four start: May 2019
  • Phase four completion: August 2019

Budget

  • For the 2019 phase - $2,700,000 which includes a $167,000 contingency. The estimate for all four phases of the project is $12,000,000.
  • This project is being funded by the deferred maintenance reserve - Residential and Hospitality Services.

Construction Junction progress update

Capital project number

  • CP16227

Questions?

Carol Cool
Project Manager
coolcaro@msu.edu (517) 353-8619