Outdoor Tennis Courts and Support Building

Overview of scope:
This project will address the pressing need for modernized and safer facilities for the university's tennis program by rebuilding the deteriorating outdoor courts and improving spectator viewing areas. In addition, a new dedicated building will be constructed to provide essential amenities, including restrooms, locker rooms, and team spaces. This facility will be strategically located to create synergies with the Clara Bell Smith Academic Center for student athletes, enhancing support for their academic and athletic development. The upgrades will ensure that the tennis program meets Big Ten standards, providing the athletes and staff with a highâquality environment that fosters success both on the court and in the classroom.
The MSU Board of Trustees authorized starting construction for this project (PDF) in February 2025.
Phase
- Construction
Budget
- $10 million provided by donation from Joan Secchia
Schedule
- February 2025: Construction start
- June 2025: Site demolition is in progress; installation of site utilities has begun.
- Substantial completion expected May 2026.
Capital Project Number
- CP24007