Transportation Services Garage

Transportation Services sign on a brick facade

Overview of Scope

The project will construct a new Transportation Services Building within the campus service district, providing a permanent location for Transportation Services’ administrative, maintenance, and garage operations. The facility will replace functions previously housed in the Central Services Building and those currently operating from Spartan Stadium’s east concourse.

Construction of the new facility requires demolition of the RHS Services Building (153 Service Road, constructed in 1962) and the University Services Building (169 Service Road, constructed in 1969). The project advances MSU’s Vision 2050: Integrated Facilities and Land Use Plan by relocating service operations from the athletics district to the campus service district and freeing space needed for the potential Spartan Stadium Modernization project. Demolition began September 2026. 


 Once completed, Transportation Services operations will be moved into a modern, purpose-built facility, with improve safety, operational efficiency, service delivery, and customer experience. The project will also support long-term campus land-use objectives and create flexibility to accommodate future campus development priorities.

Background

The Spartan Stadium Modernization project required demolition of the Central Services building, displacing the transportation Services motor pool business functions. The Spartan Stadium Modernization project requires relocation of the motor pool service garage that is currently housed in Spartan Stadium east concourse. Constructing a new building for the Transportation Services garage will improve vehicle repair capabilities which are currently limited due to ceiling heights and building constraints of the Spartan Stadium east concourse.

The Vision 2050: Integrated Facilities and Land Use Plan serves as the guiding framework for enhancements across campus, including the Athletic District. As part of the Spartan Stadium Improvements project, the Central Services building was demolished in the summer of 2025. Transportation Services offices previously located there were moved to Service District.

The creation of a new Transportation Services building will clear the way for the Spartan Stadium Modernization project by relocating a service function out of the Athletic District to the Service District.

The Service District already houses complimentary functions such as fuel station, car wash, motor pool, and parking for Transportation Services users, making it a strategic location for centralizing services that support the MSU community. 

Phase

  • Construction

Schedule

  • September 2026: Board approval 
  • Project moved the construction phase, and construction began.
  • Planned completion: June 2028

Budget

  • $24.2 M

Capital project number

  • CP25063

 

Questions?

Jason VanZee
Project Manager
vanzeeja@msu.edu 517-404-0702