Overview of Scope:

Wilson hall will undergo a renovation to transform former kitchen and dining spaces into teaching, learning and office areas for the new Technology Engineering program. this new 20,000 sq. ft. renovation will enhance the College of Engineering's presence in the area by offering cutting-edge, hands-on laboratory courses. Upgrades include HVAC, restrooms, elevator access, a new fire suppression system, and a fire alarm system replacement for the entire 300,000 sq. ft. building.

Phase

  • Design

Budget

  • $22 million

Schedule

  • June 2025: project design complete, 24%
  • Completion date: TBD

Capital project number

  • CP24047