What is being done?

Closure of Service Road to through traffic in front of T.B. Simon Power Plant and commencement of work on the project: Electrical Duct Bank Expansion and Cast Iron Water Main Replacement Along Service Road. The scope of the project will include: removal/replacement of concrete and bituminous pavement, earthwork, relocation of sanitary sewer, pavement markings, water main, duct bank, electrical vault, miscellaneous mechanical work, landscaping, and related work.

Why is this being done?

To replace cast iron water main and install new electrical duct bank and vaults

How will this impact building occupants?

This road will be closed to through traffic during the project timeframe mentioned above. At this time, there are no pedestrian detours planned around the work site. There will be intermittent construction noise in the vicinity of the project site.

Project detour has been Harrison Road / Trowbridge Road / Farm Lane. However, on Wednesday, July 8 and Thursday, July 9, detour will be changed to Harrison Road / Wilson Road / Farm Lane to accommodate resurfacing of the portion of Trowbridge Road between Red Cedar Road and Farm Lane. On Friday, July 10, detour will return to previous route. Please follow detour signage.

Who can I contact for more information?

Andrew Linebaugh, project manager, at (517) 432-7103 or linebau6@msu.edu, or IPF at (517) 353-1760.