Project Milestone Billing
Below are the project sizes, milestones and when the rates are charged:
Projects under $1 million
Have a rate of 5% of total project budget
- 50% of rate taken when project is 100% design complete
- 50% of rate taken when project is 75% construction complete
Projects $1-5 million
Have a rate of 3.75% of total project budget
- 50% of rate taken when project is 100% design complete
- 50% of rate taken when project is 75% construction complete
Projects $5-100 million
Have a rate of 3.75% of total project budget
- 15% of rate taken when project is 50% design complete
- 25% of rate taken when project is 100% design complete
- 25% of rate taken when project is 25% construction complete
- 25% of rate taken when project is 75% construction complete
- 10% of rate taken when project is 97% construction complete
Projects over $100 million
Have a rate of 3.25% of total project budget
- 15% of rate taken when project is 50% design complete
- 25% of rate taken when project is 100% design complete
- 25% of rate taken when project is 25% construction complete
- 25% of rate taken when project is 75% construction complete
- 10% of rate taken when project is 97% construction complete