Campbell Hall Renewal

Overview of Scope:
Campbell Hall opened in 1939 and requires major infrastructure repairs to its building systems. The Student Life and Engagement Strategic Plan calls for investing in existing facilities to ensure future Spartans will benefit from a strong on-campus residential system. There also is the potential for office, program, and residential housing space for the Honors College, further strengthening the student experience and elevating the academic reputation of the university.
The project will address major building systems including life safety and accessibility, along with mechanical, electrical, building envelope, and finishes. The upgrades will improve student gathering, study, and residential spaces. The project will include renovations to space to support MSU Honors College programming in the former dining room area.
The MSU Board of Trustees authorized starting construction for this project in February 2024.
Phase
- Construction
Budget
- $37.1 million
Schedule
- Construction start: May 2024
- Substantial completion: July 2025
Capital project number
- CP22116