Spartan Stadium Renovations to University Advancement: 2nd and 3rd Floors

Overview of Scope:
The project is to renovate the University Advancement (UA) space on the second and third floors of the office tower at Spartan Stadium to maximize the use of space and support ever-increasing demand on fundraising by allowing flexible meeting and donor engagement space to host alumni, donor functions, and community events. The renovations will redefine visitors' first impression and in-person engagement with UA on behalf of the university as they seek donor support.
Phase
- Construction
Budget
- $15 million
Schedule
- Construction began February 2025
- June 2025: rough framing and mechanical/electrical installation are in progress; locker rooms and meeting space for Sparty and his team have been completed
Capital project number
- CP24049