Spartan Stadium Renovations to University Advancement: 2nd and 3rd Floors

Gate J of Spartan Stadium with a large scoreboard above it emblazoned with the Spartan helmet

Overview of Scope:

The project is to renovate the University Advancement (UA) space on the second and third floors of the office tower at Spartan Stadium to maximize the use of space and support ever-increasing demand on fundraising by allowing flexible meeting and donor engagement space to host alumni, donor functions, and community events. The renovations will redefine visitors' first impression and in-person engagement with UA on behalf of the university as they seek donor support.

Phase

  • Construction

Budget

  • $15 million

Schedule

  • Construction began February 2025
  • June 2025: rough framing and mechanical/electrical installation are in progress; locker rooms and meeting space for Sparty and his team have been completed

Capital project number

  • CP24049

June 2025

interior construction site with bales of insulation, exposed steel infrastructure and construction lights

interior construction with a large expanse of concrete floor and large metal girders coated in fire retardant

Questions?

Tonino Pacifico
Project Manager
pacifico@msu.edu 517-243-0260