Hannah Administration - Electrical Utility Work

Hannah Administration

Utility work

What is being done?

Upgrading the electrical substation because the old substation is dilapidated and needs to be replaced. During this timeframe, work will take place daily from 5:00am until 7:00am. 

How will this impact building occupants?

Tuesday, July 28: HVAC systems will be down. 480v motor loads will be affected.

Wednesday, July 29: All 120v circuits and lighting circuits will be interrupted.

Thursday, July 30: Emergency lights and outlets will lose power. This will also affect the equipment connected to the emergency power.

Special Precautions: On Wednesday, July 29 and Thursday, July 30, it is recommended that facility occupants power down computers and sensitive laboratory equipment.

Please notify all personnel in your department. Your cooperation during this time is appreciated. We apologize for the inconvenience.

Who can I contact for more information?

Dan Hanses, Planner/Inspector/Analyst III, at (517) 449-7925 or dhanses@msu.edu, or ContactIPF at (517) 353-1760.