Anthony Hall – Envelope Renewal

Anthony Hall roof

Overview of Scope:

The project is anticipated to renew the hall’s building envelope by replacing roofing, insulation, and rain gutters and downspouts. It also would include extensive asbestos abatement. 

Built in 1955, Anthony Hall requires major repairs to address water infiltration issues. In 2021, the university made improvements to the building site and utility infrastructure to improve drainage in and around the building, but structural deficiencies that contribute to water infiltration remain.

The MSU Board of Trustees authorized starting construction for this project in June 2023.

Phase

  • Construction

Budget

  • $9.5 million

Schedule

  • Construction start: April 2025
  • June 2025: Stone coping rework and shingle replacement is in progress
  • Substantial completion expected November 2027

Capital project number

  • CP23046

 