Holmes Hall

Holmes Hall

Utility shutdown

What is being done?

Temporary shutdown of lab compressed air and vacuum (suction) systems in the lower level of Holmes Hall as part of renovation construction work in room C5.

Why is this being done?

The vacuum lines are being reconfigured and it is necessary to shut down the lines supply this room. To do that, the adjacent rooms also using compressed air are affected by this work. 

How will this impact building occupants?

During this shutdown, building occupants will not be able to use the vacuum lines in the room adjacent to room C5.

Who can I contact for more information?

Tonino Pacifico, project manager, at 517-243-0260 or pacifico@msu.edu, or IPF at 517-353-1760.