What is being done?
Temporary shutdown of the D area normal power breaker panels
Why is this being done?
To repair hot switch blades on PDPD1
How will this impact building occupants?
During this shutdown, there will be no electrical service to receptacles, lights, environmental chambers, and autoclaves. Night lights, standby and emergency circuits will still work.
Special precautions that need to be taken: It is recommended that facility occupants power down computers and sensitive laboratory equipment
Who can I contact for more information?
Brian Powe, skilled trades supervisor, at (517) 899-7197, or powebria@msu.edu, or Mark Alexander, Electrician, at (517) 897-6141, or IPF at (517) 353-1760.