Conrad Hall
Conrad Hall
–
Utility work
Infrastructure Planning and Facilities High Voltage Crew will be working on circuits H18 / H38. They will begin this work by installing a generator on Conrad Hall to power the building throughout the repairs. The utility work is needed to repair a leaking cable pothead on circuit H18 at the IM East building.
At 630 a.m., crews will shut down power to the entire building and then install a generator to repower the site through Saturday, March 12. On Saturday, 3/12/2022, from 6:30 a.m. to 7 a.m., another outage will occur to return power back to normal.
Special Precautions: It is recommended that facility occupants power down computers and sensitive laboratory equipment.
Dan Hanses, Planner Inspector Analyst, at (517) 927-5619 or dhanses@msu.edu, or John Nurenberg, Maintenance Services Manager - Electrical at (517) 432-0509 or jmnuren@ipf.msu.edu or IPF at (517) 353-1760.