Holmes Hall
Holmes Hall, Basement Hallway Outside of Room W15
–
Asbestos abatement
What is being done?
Abatement of approximately 6 TSI (Thermal system insulation) fittings on a 3 ft. hot water domestic main.
How will this impact building occupants?
The requester of this project is responsible for the removal of any furniture or other items which may inhibit the ability of the contractor to perform this abatement. Asbestos work areas are strictly off limits to persons who are not trained or directly involved with the project. Please respect all warning signs and danger tape.
Who can I contact for more information?
Tony Murdoch, Planner/Inspector/Analyst, at (517) 898-4454 or amurdoch@msu.edu, or IPF at (517) 353-1760.