What is being done?

Shutdown of electrical service to the building. Panel SWBD-AA to install temporary feeds to power panels during demolition and reconstruction of Duffy Daugherty. 

How will this impact building occupants?

During this shutdown, there will be no electrical service to Skandalaris, Duffy Training Room, and Duffy Player’s Lounge. Skandalaris air handlers, mechanical room pumps and the elevator will all be offline. Shutdown will also impact pools and pool mechanical room in the Training Room.

It is recommended that facility occupants’ power down computers and sensitive equipment. 

Who can I contact for more information?

Jason VanZee, project manager, at 517-432-2675 or vanzeeja@msu.edu, or IPF at 517-353-1760.  

Project Number: CP21062