The Focus - October 2020

The Focus e-newsletter from Infrastructure Planning and Facilities

IPF Communications

October 7, 2020

Grey line section separator
Grey line section separator

Board of Trustees upcoming agendas (tentative, subject to change)

​​​​​October agenda

  • Veterinary Medical Center - replace HVAC-1 and HVAC-21 (CP16192).  (Under $5M project)

December agenda

  • T.B. Simon Power Plant - install medium-pressure steam boiler (CP17198).
 
Grey line section separator

Munn Ice Arena expansion (CP18134)

  • Project milestones:
    • The current scope has been reduced to include the permanent enclosure, code and other life safety items including egress. The remaining work to complete the interior construction and furnishings will be deferred pending funding efforts by Athletics.
    • Ground floor and first floor concrete work is nearing completion.
    • Revised scope is anticipated to be complete in November, when addition will be weather tight.
  • Impact updates:
    • East/west sidewalk is closed at the south side of Munn, with pedestrian detours in place.
    • The south entrance to Munn remains closed with emergency egress only.

  

Photo of project manager, Jason Vanzee

 

For comments, questions or concerns, contact project manager, Jason VanZee, at (517) 432-2675 or vanzeeja@msu.edu. 

 

Southern elevation of Munn addition

 

Easter elevation of Munn addition

Interior of new addition looking north to existing arena entrance doors

Interior shot of addition looking south towards Munn Field, showing new exterior door bank

Interior shot of Munn Addition showing portion of area that will eventually house the Hockey Hall of History displays

Old Demonstration Hall scoreboard/clock which will be prominently displayed in the Hockey Hall of History when complete. It is hoped to renovate the scoreboard so that it will display current scores of games

New lower level of addition that will house the wet and dry home team locker rooms

Lower level area that will eventually house player lounge with easy access to west exit stairwell

Two new therapeutic whirlpool tubs have been installed and are covered to protect them from construction debris, along with an additional pool that will house an underwater treadmill for strength conditioning

Framing installed in area that will become coach's locker room and showers

Risers installed in the new team film room which will be used to review past performances

New laundry room will house equipment that can easily drain into communal trough at back of platform

 

Business College Complex - Eppley Center - Student support and capital renewal (CP18003)

  • Project milestones:
    • Demolition and abatement are 90% complete.
    • New mechanical piping and duct work has begun installation on 4th floor.
    • Air handler has been delivery and assembled in the ground floor mechanical room.
  • Impact updates:
    • Building will remain unoccupied during construction.

 

Photo of project manager, Tony Rhodes

 

For comments, questions or concerns, contact project manager, Tony Rhodes, at (517) 432-7104 or rhodesa1@msu.edu. 

 

Project manager, Tony Rhodes standing in front of construction sign at entrance to Eppley. The Eppley Center contains the largest college on campus - Hospitality and Business

 

Interior of main Eppley entrance showing elevator bank. Stairwell door will be replaced with fully glass version to encourage occupants to use stairs when possible.

Area which was student lounge area which will be developed into additional office space

New HVAC ductwork and water distribution piping are being installed in most areas of the facility

Second floor corridor

Example of typical existing office space in progress. Once work is complete, all rooms affected will have new ceilings and wall painting.

Conference Room being worked on

Department of Finance Office renovations in progress

Interior of Department of Finance office showing work in progress

Elevator vestibule on third floor

All stairwells will have new flooring/treads, painting and lighting installed

Photo of ground level new air handling unit which replaces two smaller units that were original to the building's construction

 
Gray Separator Line

 

A warm welcome

It's that time of year, when outside air temperatures are consistently cool enough to make mechanical cooling no longer necessary. Beginning next week, IPF will start shutting chillers and associated cooling towers down for the season to prepare systems for deep cleaning and winter freeze protection. If we experience a rare instance of unusually warm weather, building temperatures could rise beyond the normal setpoint, but should still be within the human comfort range. During the cold season, most MSU buildings are heated to 69 degrees during occupied hours.

  

  

Icon of thermometer and snowflake

Here are some tips to stay comfortable and use energy efficiently in campus offices:

  • Check the thermostat: Make sure there are no heat-producing appliances or equipment nearby to disrupt the temperature sensor.
  • Time for a change: Rearrange work areas to lessen exposure to cold areas and drafts. Keep books, boxes and furniture from blocking the registers.
  • Get out the sweaters: An extra layer will help with keeping warm. Scarves and shawls work, too.
  • Focus on feet: Wear warm socks and footwear. 
  • Cover the window air conditioner: Prevent cold air from coming in by using an interior cover.

Practicing smart cold-season behaviors helps the university save on heating costs and is an easy way to help MSU achieve its sustainability mission.

 

 

USE OF SPACE HEATERS ON CAMPUS

The university has established heating and cooling season building temperature policies to provide comfortable conditions in support of the university’s educational mission while advancing MSU’s energy conservation goals. Space heaters are regulated because they can create system imbalances, overload building electrical circuits and use a significant amount of energy. If used improperly, space heaters can also become a fire hazard.

  

  

icon of heater

Most campus spaces are heated to 69 degrees during the winter. Because spaces on campus vary greatly in age, construction and function, exceptions will occur. Please contact us if you experience temperature discomfort on a regular basis at (517) 353-1760. We will identify the source of the problem and work to provide a comfortable work environment.

Where space temperatures fall within university guidelines, several low wattage personal heaters have been approved that meet safety and efficiency guidelines. A list of approved heaters available through Spartan Marketplace can be found here.

NoteThis information does not pertain to MSU Residential and Hospitality Services facilities.

 

 

Keeping campus water safe and reliable

The new Water Treatment Plant and storage tower on south campus is but one of the many initiatives that IPF has undertaken over the past several months to improve the aesthetics of campus water and continue its safe and reliable delivery.

Here are a few of the other projects we've been involved in:

  

  

photo of open hydrant

Distribution system replacement - Summer 2020 saw the replacement of the first-floor water mains that feed the branches of pipes distributing water to the rest of Wilson, Holden and Owen halls. At the same time, additional valves were added to the system to aid in isolating future trouble spots, which will help make repairs quicker and less inconvenient to building occupants.

Hydrant flushing - IPF crews are continuing flushing of various hydrants across campus to expedite the removal of iron sediment that had accumulated in the water distribution system prior to the switchover to the new treatment plant.

Corrosion testing - Water Treatment Plant staff have installed "corrosion coupons", pre-weighed metal strips made of the same materials as the pipes they are hung in, to estimate the rate of metal corrosion following 90 days of exposure to the water in the system. By comparing the start and end weight of these "coupons", staff can accurately adjust the amount of corrosion-inhibiting additive added to the water so that pipes are better protected against water's natural corrosive properties.

IPF is committed to ensuring that the campus water supply remains safe, reliable and sustainable.

 

SURPLUS STORE AND RECYCLING CENTER TOWN HALL - BROKERING OUR COMMODITIES

Join SSRC online on Thursday, Oct. 22 at 7 p.m., when guest Jill Brown of Metro Recycling discusses brokering of our recycling commodities. SSRC works with Metro to sell our recyclable materials. Jill will discuss Metro's role in managing recycled materials, the importance of recycling in Michigan and the impacts of COVID-19 on recycling markets. An open Q&A session will follow. Register here

 

  

  

photo of msu recycling center

Gray section separator line

  

IPF carpenter Steve Rondeau assembles one of the replacement doors for the Auditorium

IPF craftspeople recreate historic Auditorium doors

Eighty years of wear, tear and unforgiving weather have taken their toll on the beautiful doors that adorn the facades of the MSU Auditorium and Fairchild Theater, and replacement has become necessary. But who could replicate the intricate and unique custom-carpentered construction of these wood and glass works of art, while being good stewards of the university’s precious resources? IPF skilled trades staff, of course.

 

  

Events Office Angie Zell and Jamie Talbert in their office prior to the COVID outbreak

Get to know your IPF crews: Campus Events Office

With much of fall instruction being done online and many students, staff and faculty working remotely, the campus is certainly quieter than it has been since its inception. But behind that tranquil façade there is still a myriad of activity going on, and helping coordinate much of that activity is the IPF Campus Events Office.

 

  

IPF staff brainstorm on ideas on how to improve the existing IPF hiring and onboarding process

IPF hiring and onboarding gets a RAPID reboot

The IPF Process Improvement Team, in collaboration with IPF Human Resources, has employed a new process improvement methodology, known as RAPID, to make the job of hiring and onboarding new full-time employees easier and more consistent.

  

 
Gray line section separator

  

IPF Landscape Services crew members Jacob Paivarinta and Jill Arthur update Sparty's flower beds with beautiful mums to celebrate the autumn season
IPF Landscape Services crew members Jacob Paivarinta and Jill Arthur update Sparty's flower beds with beautiful mums to celebrate the autumn season

  

T.B. Simon Power Plant's Mike Thiry removes the internals of #3 condensate returns polisher so tank can be sent out for re-coating. Mike is working alone within in a permit-required confined space with a confined space attendant (not pictured) stationed outside and beyond the 6-foot social distancing guideline. A face mask makes it difficult for the employee working inside the confined space to communicate with the confined space attendant to coordinate and work safely.
Performing one of the many jobs necessary to keep power flowing to campus, T.B. Simon Power Plant's Mike Thiry removes the internals of #3 condensate returns polisher so tank can be sent out for re-coating. Mike is working alone within in a permit-required confined space with a confined space attendant (not pictured) stationed outside and beyond the 6-foot social distancing guideline. A face mask makes it difficult for the employee working inside the confined space to communicate with the confined space attendant to coordinate and work safely.

  

Service technician installing and programming new autonomous mowers to be used at Bryan/Brody Halls and Demonstration Hall.
Landscape Services staff have had great results with the autonomous mowers currently taking care of the green spaces at ISTB and Cowles House, and so three additional units have been purchased to serve green spaces around Demonstration Hall and Bryan/Brody Halls.

  

New vehicle occupancy rule signs installed in response to COVID
IPF Communications and Sign Shop staff created new vehicle occupancy guideline signs that have been installed in all IPF vehicles and will soon be installed in all motor pool fleet vehicles as well.

  

Recycling Center staff install the plastic cover over the new vermicomposting hoop house
MSU Recycling Center staff and Professor John Biernbaum (Horticulture) install the plastic cover over the new vermicomposting hoop house that will convert food waste to a nutrient-rich soil amendment via the digestive power of worms.

  

 
Grey line section separator

  

Twitter post regarding Landscape Services plantings a the MSU Union

  

Instagram post regarding custodial work being done at MSU Library

  

Facebook post regarding Mark Rokita's recent promotion to Set Up crew manager

  

Gray Line Section Separator

Feedback

We welcome any comments, questions or suggestions on how we can improve communications with you, our campus partners.

Please forward your comments to the IPF Communications department at IPF.Communications@msu.edu

Thank you!

Grey line section separator