Facilities Focus - September 2019 - Volume 5

Facilities Focus logo featuring various IPF staff members at work

IPF Communications

September 9, 2019

SUBSCRIBE TO GET THE FACILITIES FOCUS NEWSLETTER DELIVERED TO YOUR INBOX!

   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .

    .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .

Graphic of Barry the Barrel and wording Construction Junction

   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .

Board of Trustees upcoming agendas

October agenda

  • No construction projects scheduled for Step 2 (Authorization to Proceed) or Step 3 (Bid and Contract Award) approval at this time.

​​​​​December agenda

  • For Step 2 (Authorization to Proceed)
    • T.B. Simon Power Plant - install medium-pressure steam boiler (CP17198)
    • Business College Complex - capital renewal (CP18003)

   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .

Munn Ice Arena - expansion (CP18134)- update

  • Project milestones:
    • Mobilization of construction trailer and equipment is complete.
    • Clearing of earth is complete.
    • Site excavation has commenced.
    • Demolition of south building exterior is complete.
  • Impact updates:
    • East/west sidewalk is closed at the south side of Munn, with pedestrian detours in place.
    • The south entrance to Munn is closed.

 

Photo of Jason Van Zee

 

For comments, questions or concerns, contact project manager, Jason Van Zee, at (517) 432-2675 or vanzeeja@msu.edu  

Mass excavation exposes existing exterior wall
Mass excavation exposes existing exterior wall
Existing canopy demolition in progress
Existing canopy demolition in progress
Demolition of existing entrance canopy complete. Wing wall and stair demolition in progress.
Demolition of existing entrance canopy complete. Wing wall and stair demolition in progress.
Stair demolition in progress
Stair demolition in progress
Mass excavation at east half of addition
Mass excavation at east half of addition

   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .

Hubbard Hall - exterior masonry restoration and window replacement - phase four (CP16227) - wrap up

  • Project milestones:
    • All four phases of the project are now complete.

 

Photo of Carol Cool

 

For comments, questions or concerns, contact project manager, Carol Cool, at (517) 353-8619 or coolcaro@msu.edu 

Phase four window removal begins
Phase four window removal begins
Installation of the new windows underway
Installation of the new windows underway
Working on the final drop
Working on the final drop
Main window replacement complete
Main window replacement complete
Lifting window frame into the stairwell for the completion
Lifting window frame into the stairwell for the completion

   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .

Cowles House - Addition 3 and site renovations (CP17186) - update

  • Project milestones:
    • Demolition is nearing completion.
    • New foundations and interior framing installations are underway.
  • Impact updates:
    • Site barricading with pedestrian and traffic controls ongoing.
    • Facility operations to resume upon completion, March 2020.

 

Photo of Chris Barnes

 

For comments, questions or concerns, contact project manager, Chris Barnes, at (517) 355-1628 or barne137@msu.edu

Rendering of completed terrace area
Rendering of completed terrace area
Existing Terrace Room demolition
Existing Terrace Room demolition
Living Room demolition
Living Room demolition
New Terrace Room foundation installation in progress
New Terrace Room foundation installation in progress
New Garage foundation installation in progress
New Garage foundation installation in progress
Foundation for new terrace area
Foundation for new terrace area

   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .

Water distribution - campus water system improvements (CP16086) - update

  • Project milestones:
    • Water tank was raised to the top of its concrete support pedestal on Aug. 9.
    • Water Treatment Plant exterior is complete. Remaining sitework and final paving will be completed by the end of September.
    • Interior work in the Water Treatment Plant is nearing completion. Testing, balancing and commissioning the various systems will happen from mid-September through October.
  • Impact updates:
    • Water tank roof will be installed and painted during September.
    • The center derrick crane, used to construct the tower, will be removed.
    • Interior of water tank will be painted and disinfected, ready for operation in early November.

 

Photo of Robert Nestle

 

For comments, questions or concerns, contact project manager, Robert Nestle, at (517) 355-3372 or nestle@msu.edu

Water Tower on Aug. 8
Water Tower on Aug. 8
Water Tower on Aug. 9
Water Tower on Aug. 9
Water Treatment Plant - exterior
Water Treatment Plant - exterior
Water Treatment Plant - water filtration tanks
Water Treatment Plant - water filtration tanks
Water Treatment Plant - chlorine feed and storage
Water Treatment Plant - chlorine feed and storage
Water Treatment Plant - Water Lab
Water Treatment Plant - Water Lab
Water Treatment Plant - Control Room
Water Treatment Plant - Control Room
Watch the time-lapse video of the Aug. 9 water tank raising.

 

 

Watch the progress of construction on the project webcam.

View from project webcam
View from project webcam

   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .

Music Building Addition (CP17077) - update

  • Project milestones:
    • Brick veneer application is underway.
    • Rehearsal Room finishes and glazing installation has begun.
    • Interior renovation work to support fall class activity is 90% complete.
  • Impact updates:
    • Pedestrian travel diagonally through the site is being maintained.
    • Noise impacts due to typical construction activity are expected throughout the project.

 

Photo of Todd Wilson

 

For comments, questions or concerns, contact project manager, Todd Wilson, (517) 432-4355 or wilsont@msu.edu

New terrazzo floor finishes in existing front lobby
New terrazzo floor finishes in existing front lobby
View from second-floor classroom (206) into the Pavilion lobby space
View from second-floor classroom (206) into the Pavilion lobby space
Interior of Hollander Hall - looking south at new plaster ceiling
Interior of Hollander Hall - looking south at new plaster ceiling
Interior of Hollander Hall - looking north at performance shell framing
Interior of Hollander Hall - looking north at performance shell framing
View from balcony entrance over Murray Hall
View from balcony entrance over Murray Hall
Brick veneer application on the north face of Medium Rehearsal
Brick veneer application on the north face of Medium Rehearsal

 

 

Watch the progress of construction on the project webcam.

View from project webcam
View from project webcam

   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .

FRIB - Cryogenic Assembly Building (CAB) (CP17240) - wrap up

  • Project milestones:
    • Building construction is substantially complete.
    • Punch list items and final commissioning are complete.
Photo of Jessica Kolp

 

For comments, questions or concerns, contact project manager, Jessica Kolp, (517) 908-7746 or kolp@frib.msu.edu

Overhead crane installed and tested
Overhead crane installed and tested
Mechanical mezzanine area
Mechanical mezzanine area
People currently occupying building
People currently occupying building
Initial rendering of building interior
Initial rendering of building interior
View of completed building interior
View of completed building interior
Initial rendering of building exterior
Initial rendering of building exterior
View of completed building exterior
View of completed building exterior

   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .

Valuable information for our campus customers logo

   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .

Streamlining processes cuts construction planning time 

The MSU Board of Trustees recently revised the university's Capital Project Planning and Approval Policy. The revision, initiated by Infrastructure Planning and Facilities’ Planning, Design and Construction department staff increases the threshold for Board of Trustees’ approval of construction projects from $1 million to $5 million and effectively shortens the planning time for many projects. 

   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .

You too can become a Waste Warrior!

Waste Warriors are faculty and staff members who are committed to help campus reduce, reuse, recycle and refurbish materials. Those who sign up for the program will be offered additional waste diversion services such as surplus item collection, composting, and glass and Styrofoam recycling.

   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .

Opportunities for women in the skilled trades industry

The Lansing State Journal recently published a picture gallery titled "The Women in Professional Trades" which included four of Team IPF's finest; preventative maintenance worker Courtney Hasse, maintenance mechanic Sheryl Shay, mason April Toune and trades helper Lindsay Hasse. Theirs' are but a few of the many stories of successful women employed in the skilled trades.

Women who are interested in pursuing a career in the skilled trades should check out the Women in Skilled Trades (WIST) Facebook page. There you will find information about their Apprenticeship Readiness Program, which prepares women for successful careers in the skilled trades industry, and provides opportunity to connect with other tradeswomen.

   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .

MSU Surplus Store and Recycling Center's ten-year anniversary

The SSRC celebrates its tenth year at the Green Way facility, and you get the presents!

From Sept. 5 through 13, their "Tenth Anniversary Triumph" will include unique sales, tours and other events designed to engage the MSU community and valued customers. There will be sales in different departments including computers, MSU memorabilia/art, industrial and lab equipment, furniture, household items and Spartan UpCycle brand products.

MSU Athletics fans will get great deals on a large selection of Spartan athletic apparel on Tuesday, Sept. 10, from 7:30 a.m. - 5:30 p.m.

Hope to see you there!

   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .

Bogue Street protected bike lanes open

On Thursday, Aug. 15, a ribbon-cutting event was held for the opening of the Bogue Street protected bike lanes project. On hand were university President Samuel L. Stanley Jr., Provost June Youatt, Executive Vice President Satish Udpa and East Lansing Mayor Mark Meadows.

This pilot project will continue through Oct. 31, at which time it will be evaluated for its effectiveness at improving safety for pedestrians and bicyclists.

   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .

Hiring flyer for Landscape Services laborer positions

   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .

Stories from Team IPF logo

   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .

 

Get to know your IPF crews: Steam, Distribution and Outside Weld

Red water…black water…root balls…no, it’s not some kind of freaky energy drink; it’s just another day in the life of a Steam, Distribution and Outside Weld crew member. 

Photo of some of the members of the Steam, Distribution and Outside Weld crews

   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .

 

Photo of Materials and Logistics parts shelves

Electrical commodity contracts result in powerful savings

Last summer, IPF Materials and Logistics, working in close collaboration with University Services – Purchasing, established the first commodity purchasing contracts in IPF history, which have saved the university over $26,000 to date. 

   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .

 

Turbine refurbin' keeps energy surgin'

Every year, Power and Water staff members perform an overhaul of one of the five steam turbine/generators at the T.B. Simon Power Plant. This preventative maintenance work is crucial to ensuring the university, its students, staff and research activities are supplied with reliable electric service.

Photo of power plant worker using hoist to lift turbine rotor out of its housing

   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .

Feedback

We welcome any comments, questions or suggestions on how we can improve communications with you, our campus partners.

Please forward your comments to the IPF Communications department at IPF.Communications@msu.edu

Thank you!

   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .