The Focus - September 2020

The Focus e-newsletter from Infrastructure Planning and Facilities

IPF Communications

September 14, 2020

Grey line section separator
Grey line section separator

Board of Trustees upcoming agendas (tentative, subject to change)

​​​​​October agenda

  • Veterinary Medical Center - replace HVAC-1 and HVAC-21 (CP16192).  (Under $5M project)

December agenda

  • T.B. Simon Power Plant - install medium-pressure steam boiler (CP17198).
 
Grey line section separator

Water distribution - campus water system improvements (CP16086)

  • Project milestones:
    • On Wednesday, Aug. 26, the new Water Treatment Plant and storage tower began supplying treated water to much of main campus.
    • The existing Reservoir is in the process of being isolated from the distribution system and will be decommissioned.
    • The electric pumps that previously pressurized and distributed water throughout the system have been shut down. The storage tower now provides adequate pressure for distribution through gravity feed.
    • Flushing of the water distribution system is ongoing, to expedite the removal of accumulated sediment.
    • Corrosion-control studies are in process, allowing for fine tuning of treatment plant operations.
    • Shop space in the old Reservoir will be used to house the IPF Plumbing Shop, which has outgrown its space in the IPF building.
Photo of Tom Silsby

 

For comments, questions or concerns, contact Water Works supervisor, Tom Sislby, at (517) 884-7110 or silsbyth@msu.edu.

Exterior shot of new Water Treatment Plant and Storage Tower

Interior shot of Water Treatment Plant

Interior shot of Water Treatment Plant

Interior shot of Water Treatment Plant testing lab

Interior shot of Water Treatment Plant Control Room

Photo of Tom Silsby standing inside bottom of storage tower base

View from interior of storage tower base looking up at bottom of 2 million gallon tank

Photo of testing faucets at the Water Treatment Plant lab, showing the improvement in water aesthetics as the water travels from well source through treatment and finally at end of treatment

Photo of exterior of old water reservoir, now decommissioned

Photo of reservoir crew member switching off reservoir water pumps to switch over to the gravity-fed storage tower

 

T.B. Simon Power Plant - R.I.C.E. - construct original building (CP17197)

  • Project milestones:
    • Project is approximately 80% complete, on budget and on time for late December completion.
    • Electrical equipment that serves and supports the new R.I.C.E. facility has been fully connected and is receiving power from the power plant.
    • Fire alarm testing is complete.
    • Pressure testing and insulating of cooling water piping is complete.
    • Insulated exhaust duct for all three engines has been installed.
    • Installed motors in intake fans on north side of engine hall.
    • Power Plant staff are in process of training on facility and equipment operations.
  • Impact updates:
    • Construction traffic continues around T.B. Simon Power Plant site.
Photo of Chris Barnes

 

For comments, questions or concerns, contact project manager, Chris Barnes, at (517) 355-1628 or barne137@msu.edu

Photo of exterior of RICE facility

Exterior of the R.I.C.E. site, showing the three exhaust gas silencers

Cooling fans

Transformer and switchgear

Interior photo of RICE facility showing lift in operation

Interior overhead shot of RICE facility showing three RICE units in place

Interior photo showing crew member working on one of the RICE units

Close up shot of one of the RICE units

 

Strategic academic development - STEM teaching, learning and interdisciplinary research facilties (CP17133)

  • Project milestones:
    • Windows have been installed in both the Shaw Lane Power Plant section and new classroom addition.
    • New zinc metal roof has been installed on the old power plant section.
    • Artifact walls (art installation) in the old power plant section have been installed.
    • Modifications to the remaining boiler have been completed for safety and are ready for 3-D scanning by the artist.
    • Polished concrete floors are complete in the labs in the south addition.
    • Metal lab casework and fume hood installations are ongoing.
    • Southern section of the site was released for landscaping and for pedestrian access on campus.
    • Tile has been installed in the south addition restrooms.
    • Exterior masonry veneer is complete on north addition.
    • Drywall and painting on the third floor Computer Science room and Physics space has been completed.
    • The auditorium lecture-style seating concrete floor has been placed.
    • In-floor electrical rough-in is complete.
  • Impact updates:
    • Construction traffic will continue in and around the construction site until February 2021.
Photo of Ken Gottschalk, project manager

 

For comments, questions or concerns, contact project manager, Ken Gottschalk, at (517) 353-7234 or gottsc20@msu.edu

Aerial view of north end of construction site

Aerial view of west side of construction site

Aerial view of southwest side of construction site

Photo of south addition exterior

Photo of south addition exterior showing hardscape and landscape work

Photo of south addition exterior showing hardscape and landscape work

Photo of west side of construction site showing roofing and window work on old Shaw Lane Power Plant section

Interior photo showing art installation made from old valve handles from the Shaw Lane Power Plant

Photo of interior corridor

Photo of interior learning/teaching space

Photo of interior learning/teaching space

Photo of one of the facilities bathrooms in progress

 

Duffy Daugherty - S.A.A.C. - alterations to Skandalaris Football offices and Hall of History (CP18074)

  • Project milestones:
    • Enclosure of west addition is complete.
    • Construction of new office spaces is complete.
    • Finishing and furniture installation is in progress.
    • Exterior wall glass has been installed.
    • Metal panels are scheduled for installation by end of month.
    • Interior modular wall panels and exterior metal panels are not scheduled for installation until later in month due to COVID-related delays in procurement.
  • Impact updates:
    • Sidewalk running along the east side of Chestnut Rd., between Parking Lot 78 and Shaw Lane, will remain closed until completion of construction.
Photo of project manager, Jason Vanzee

 

For comments, questions or concerns, contact project manager, Jason VanZee, at (517) 432-2675 or vanzeeja@msu.edu. 

Exterior photo of Duffy addition - from the west

Photo of construction in progress on new first floor display cases

Photo of construction in progress on new first floor display cases

Photo of new second floor reception desk

Photo of one of two cubicle rows that flank center conference room

Photo of new conference room

Photo of under table led lighting in conference room

Photo of coach Tucker's office

Photo from second floor of new first floor display case installation

Looking down winding stairway from second floor landing

 
Gray Section Separator Line

Working to keep campus indoor air safe

Current research shows that the COVID-19 virus cannot be effectively transmitted via building HVAC systems.

However, out of an abundance of caution for the safety of our students, faculty and staff, IPF is in the process of evaluating the HVAC systems of over 1200 campus spaces, following CDC, the American Society of Heating, Refrigerating and Air‐Conditioning Engineers (ASHRAE) and OSHA guidelines for ventilation and filtration.

We are installing high-efficiency filters where they are needed and are in the process of procuring UV space sterilizers for elevators. Read more

 

 

 

Photo of Bio Engineering building

 

Surplus Store and Recycling Center town hall - Brokering Our Commodities

Join SSRC online on Thursday, Oct. 22 at 7 p.m., when guest Jill Brown of Metro Recycling, discusses brokering of our recycling commodities. SSRC works with Metro to sell our recyclable materials. Jill will discuss Metro's role in managing recycled materials, the importance of recycling in Michigan and the impacts of COVID-19 on recycling markets. An open Q&A session will follow. Register here

 

 

Photo of MSU Recycling Center

 
Grey line section separator

 

Architects rendering of new landscaping at Vet Med north entrance

Transplanted IPF landscape architect creates a tail wagging design

Yun Cao, IPF landscape architect, was recently transferred to Landscape Services, where she has hit the ground running with a donor-approved design for a new north entrance to the Veterinary Medical Center. Read more

 

Photo of IPF custodian Michelle Goad in mask

IPF custodians help keep essential workers safe

They show up for work every day, facing the COVID virus head on, with an arsenal of equipment and products designed to help keep the rest of campus healthy and productive. Read more

Grey line section separator

  

 
Photo of Dr. John Biernbaum and Recycling Center staff in process of constructing vermicomposting hoop house.
Dr. John Biernbaum (Horticulture), and Surplus Store and Recycling Center staff members are in the process of constructing a hoop house to contain the SSRC's upcoming on-site vermicomposting operation. Through the digestive power of worms, food scraps will be turned into nutrient-rich compost that will be sold in the Surplus Store.

  

One of six mobile conductor's shields fabricated for the College of Music by IPF Alterations and Improvements and Carpentry Shop craftsmen.
One of six mobile conductor's shields fabricated for the College of Music by IPF Alterations and Improvements and Carpentry Shop craftsmen. To date, this team has order over 13,760 square feet of Polycarbonate used in the fabrication of shielding in over 35 campus buildings.

  

Munn Field showing striped mowing effect
IPF's autonomous mower, Mow-bot, has been keeping Munn Field looking good all summer. It was recently equipped with a striping kit, which not only makes the field look cool, it makes the turf healthier by allowing the sun to hit all portions of the grass.

  

 
Grey line section separator

  

Twitter post thanking IPF for all its hard work

  

Labor Day Instagram thank you from President Stanley

  

Facebook post about new Water Treatment Plant

  

Gray Line Section Separator

Feedback

We welcome any comments, questions or suggestions on how we can improve communications with you, our campus partners.

Please forward your comments to the IPF Communications department at IPF.Communications@msu.edu

Thank you!

Grey line section separator